top of page

Seven Disputes, Seven Paper Trails: What a Middle East Hotel Retrofit Really Cost Its Owner

Writer: Steven Hunt
Steven Hunt
6 days ago
12 min read

A Case Study on Contract Risk in Middle East Hotel Renovations and PIPs


The (fictional) Coral Bay Resort is a 400-key beachfront property in the (fictional) Emirate of Sharjat-Al-Bahr. In late 2025 its owner signed a PIP-driven renovation contract with Halcyon Build LLC, a, (fictional) regional fit-out contractor, to reposition the property under a new upscale lifestyle brand, Sihha wa Taraf Collection (also fictional), under a separate management agreement with the brand's operating company. The renovation covered three towers, closed and reopened in sequence so the hotel could keep trading through the works. Over the following thirteen months, seven incidents tested the contract — and the owner's own preparation — in turn.


1. The Wall Comes Off (Unforeseen Site Conditions)


What happened

In month two, stripping back a 1990s dry-lined wall in Tower A, Halcyon's site team found corroded MEP risers and undocumented structural alterations from a previous fit-out that nobody on either side knew about — the kind of condition a retrofit only discovers once existing fabric is actually opened up, where a new-build's ground investigation would have settled the same question months earlier. Halcyon waited close to the 28-day notice deadline before telling the Engineer, well within its rights under the contract, and once notice was given the Engineer took several weeks more to request and agree a price for the repair and confirm the resulting extension of time before instructing it as a Variation. Six weeks passed between discovery and an agreed, instructed scheme — none of it because the repair itself was complicated.


The fix

Unforeseen physical conditions are a bigger risk on a retrofit than on most other construction, because much of the existing structure is covered up rather than exposed to survey — a fit-out only learns what is behind a wall as the works open it up, where a new-build's ground investigation settles that question before the contract is signed. A pre-contract survey helps but does not remove the risk, and is often unrealistic on cost and time in any event; what it really buys is pricing and delay certainty, not the absence of a problem. The larger exposure is the timetable standard FIDIC allows once a condition is found. Sub-Clause 4.12 gives Halcyon the right to notify and claim relief, but Sub-Clause 20.1 lets that notice come up to 28 days after Halcyon became aware, and once notice is given, Clause 13 lets the Engineer instruct the repair as a Variation only after it has typically requested a price for the work and confirmation of the time impact — unamended FIDIC puts no short deadline on either. A contractor with no incentive to move faster can use the full 28 days, then let the pricing and time discussion run for weeks more, turning routine administration into leverage. A retrofit needs a regime that binds to a shorter clock, as a condition precedent: notice within days, not 28; materials for the likely fix identified and procurement started before the price is even agreed; and an equally short, fixed period for the Engineer to instruct the Variation, receive a price, and confirm the time consequence — with the contractor obliged to take reasonable steps to protect the programme throughout. Handled this way, the sequence from discovery to an agreed, instructed scheme runs in days, not the weeks or months.

Drafting note: amend Sub-Clause 4.12, or add a Particular Condition on concealed conditions, to bind both sides to a short clock. Require contractor notice within days of discovery, not the general 28-day period, with replacement materials identified and procurement started before the price is agreed. Require the Engineer to request any price and time proposal immediately on notice, and to instruct the Variation and confirm its value and time consequence within a fixed, short period of receiving it — with the contractor's proposal deemed accepted if the Engineer misses that deadline. Add an express obligation on the contractor to take reasonable steps to protect the programme in the meantime, with the reasonable cost of doing so recoverable as part of the same claim. The aim is that neither side can turn ordinary administration — sitting on notice, sitting on a pricing request — into weeks of delay.


2. The Brand Steps In (Unauthorised Instructions)


What happened

In month five, Sihha wa Taraf's technical services director visited site, decided the bathroom stone specification did not meet the brand's global standard, and told Halcyon's site manager directly to substitute a more expensive imported marble. Halcyon complied to keep the programme moving, assuming a formal variation would follow. It did not. When Halcyon submitted the cost six weeks later, the owner's project manager had no record of ever approving the change, and Sihha wa Taraf's representative denied giving an instruction "to change the contract" — only "guidance on brand compliance."


The fix

The gap that let this happen sat in the owner's own paperwork, not Halcyon's. A construction contract and a management or franchise agreement that both bar the brand's technical team from instructing the contractor directly — and that require any brand-originated standard to be routed through the Engineer for pricing and formal instruction before work proceeds — would have forced Sihha wa Taraf's representative to raise the marble issue on the record, giving the owner the chance to see the cost, and to say no, before the stone was ordered. The gap is also a liability allocation problem, not just a communication one: nothing in the construction contract stopped the technical director from speaking to Halcyon's site manager, and nothing in the management agreement made the brand answerable to the owner for the cost of an instruction its own staff gave outside that channel. A clause silent on brand access to the contractor's team is not neutral — it defaults to whichever counterparty's representative reaches the site manager first, which on a branded renovation is usually the brand's.

Drafting note: a clause that actually holds does three things at once — defines "Brand Instruction" broadly enough to catch informal guidance as well as a formal written standard; provides that no Brand Instruction affects scope, time or cost unless and until the Engineer issues it as a Variation; and requires the management agreement to indemnify the owner for any cost the brand's own personnel cause by instructing the contractor outside that channel. Include only the first element and the brand's representative has no reason to stop giving instructions directly — there is a paper channel, but no consequence attached to ignoring it.


3. The Missed Wing (Liquidated Damages)


What happened

Tower B was due to reopen before a high-occupancy holiday period the owner had priced into its liquidated damages rate. Halcyon overran by eleven days. The owner issued an LD notice calibrated to a room-revenue figure it had never disclosed at tender, and when Halcyon queried the basis for the rate, the owner initially could not produce the calculation.


The fix

Under UAE law, that gap was a liability in itself: a court or tribunal has a broad, mandatory power to adjust liquidated damages to actual loss, and any contractual attempt to exclude that power is void[1] — so an LD rate the owner cannot substantiate is one a tribunal can reduce, sometimes substantially. The rate was eventually renegotiated by agreement rather than tested — a compromise the owner would not have needed to make if it had built and retained the room-revenue calculation behind its LD rate at the time the contract was signed, ready to produce the moment it was queried rather than reconstructed under pressure once a dispute had already started. A sharper fix goes beyond documentation: a single LD rate fixed for the whole property assumes every tower is worth the same to the business on its own reopening date, which is rarely true mid-renovation. Structuring the rate on a sliding scale tied to the occupancy and revenue status of the other towers at each phase, rather than one flat figure set at signature, gives the owner a rate calibrated to the loss actually at stake at each stage — and one it can defend on its own terms rather than simply produce on request. There is a second reason this matters specifically under UAE law: the court's Article 340 power to adjust the rate is engaged when the rate looks less like a genuine pre-estimate of loss than a number chosen to deter delay. A rate that visibly tracks the revenue actually foregone at each phase of a sequenced reopening is harder to characterise as arbitrary than one flat figure applied regardless of which tower is late. That does not immunise the clause — the power to adjust cannot be excluded by drafting — but it narrows the gap a tribunal can find between the contracted rate and the loss it is supposed to represent.

Drafting note: a sliding-scale LD clause ties the daily rate for each tower's delay to a schedule of room-nights and average rate at risk during the specific weeks that tower's completion governs, cross-referenced to the same occupancy forecast used to underwrite the deal — so the figure produced under pressure is not new documentation created for the dispute, it is the model the owner was already running.


4. The Reflagging Scare (Contract Interface Risk)


What happened

In month eight, with Tower B still not fully snagged, Sihha wa Taraf's regional office wrote to the owner noting that the delay was approaching a threshold in the management agreement's own PIP completion schedule — a schedule the construction contract had never been drafted with reference to. For several tense weeks the owner faced two overlapping problems at once: a construction delay it could pursue Halcyon for, and a potential franchise compliance notice from Sihha wa Taraf that the construction contract could do nothing about.


The fix

The exposure was real precisely because it had been priced only once. An owner negotiating a termination-for-default and step-in clause that lets it remove or replace an underperforming contractor without paying more than work properly executed and stored materials is protecting only half its position if the parallel management agreement's own PIP deadline was never cross-referenced against the construction programme at drafting stage. Owners who negotiate the two agreements as a single, coordinated timetable do not find themselves managing a contractor dispute and a brand relationship crisis on two different clocks. The mismatch here was not only calendar; it was jurisdictional. Construction contracts in this market are typically drafted and enforced onshore, while management and franchise agreements are commonly governed by a different law and seated in a different forum entirely. An owner facing simultaneous construction delay and franchise non-compliance is not just running two clocks — absent coordination at drafting stage, it is running two sets of advisers in two systems, each working from a file the other cannot see.


5. The Handover Stand-Off (Taking-Over and Retention)


What happened

Tower C's snagging list ran long, and Sihha wa Taraf's own technical inspectors declined to sign off despite the Engineer being willing to issue the Taking-Over Certificate. Retention stayed locked while the owner, the Engineer, and the brand each waited for someone else to move — three weeks of stalemate, resolved only when a joint inspection, with the Engineer, the owner's project manager, and Sihha wa Taraf's inspector walking the snagging list together, closed out ninety per cent of the items in a single day.


The fix

The three weeks lost were entirely a process failure. An owner that fixes the Taking-Over Certificate trigger to the brand's own technical sign-off in advance and builds the joint inspection into the contract as a defined milestone rather than an informal courtesy, gets the one-day close-out that eventually happened anyway — three weeks earlier, with retention released on schedule instead of held hostage to a process nobody owned. The deeper fix is a backstop, not just a trigger: tying the certificate to the brand's sign-off without a deemed-satisfaction date if the brand simply does not respond only relocates the same open-ended risk from "the Engineer won't certify" to "the brand won't inspect." A workable clause fixes a period after which the brand's silence is treated as satisfaction, so retention cannot be held indefinitely hostage to a party that is not even a signatory to the construction contract.


6. The Frozen Certificate (Payment Certification)


What happened

A single disputed variation item, worth less than two per cent of the current payment application, led the owner's certifier to withhold the entire certificate pending resolution. Halcyon, cut off from an otherwise undisputed payment, slowed progress on two unrelated workstreams within the week, and what had been a narrow valuation disagreement became a programme problem across the whole site.


The fix

This was avoidable through payment administration alone, without touching the merits of the underlying dispute. Certifying and paying the undisputed portion of every application in full, and ring-fencing only the specific line item genuinely in dispute, denies a contractor the real grievance — and the real excuse to slow down elsewhere — that an owner creates by withholding an entire certificate over one contested item. The exposure is not only relational. Depending on how the payment clause is drafted, withholding a certified sum without following the contract's own notice-and-basis procedure for doing so can itself be treated as a breach of the payment mechanism, potentially giving the contractor a contractual right to suspend rather than merely a practical incentive to slow down. Ring-fencing the disputed line item protects the owner on both fronts: it keeps the contractor moving, and it keeps the certifier's own conduct defensible if the withholding is ever challenged.


7. The Quantum Dispute at Close (Dispute Resolution Strategy)


What happened

By project close, Halcyon and the owner had one live disagreement left: quantum on the concealed-conditions claim, worth roughly AED 2.1 million. Rather than referring it to arbitration under the contract's default clause, both sides — reluctantly, on Halcyon's side — put it to an ad hoc DAB. A single adjudicator, briefed with a document-grounded chronology each side had built from its own project record, issued a decision within six weeks. Neither side loved the result. Both paid it and moved on.


The fix

This is the one incident in the sequence where the owner's preparation had already worked. Naming and resourcing an ad hoc DAB mechanism at negotiation stage, rather than leaving the contract's arbitration clause as the only route, is what made a six-week resolution possible instead of a multi-year one. The enforcement caveat is more specific than "not always straightforward": a DAB decision, unlike an arbitral award, is not itself enforceable under the New York Convention, because it is not an award. A party that ignores a binding DAB decision creates a fresh dispute — non-compliance with a contractual obligation — which typically has to be referred back into arbitration before it becomes an enforceable award. Naming the mechanism at negotiation stage solves the speed problem; it does not solve the enforcement problem, which is why a DAB decision's real force in this market is persuasive and reputational rather than self-executing, and why both sides here had every practical incentive to treat it as final even though, strictly, neither was yet bound to.

None of these seven incidents involved a defect the contractor concealed, a brand acting in bad faith, or a dispute either side wanted. Each was the predictable consequence of a gap the owner could have closed before the contract was signed: a survey not commissioned, an instruction channel not defined, a calculation not retained, two agreements not read together, an inspection trigger not fixed in advance, a certificate withheld in full over a fraction of its value. The one incident that resolved quickly did so because the owner had, in that instance, already done the preparatory work. The lesson of Coral Bay is not that retrofit projects are unusually dispute-prone — it is that the disputes they do produce are unusually traceable, after the fact, to a specific clause, a specific piece of paper, or a specific certificate the owner did not handle correctly before or during mobilisation.


A Working Checklist

Before the next renovation or PIP tender is issued and signed, an owner should be able to answer yes to each of the following:

  • Does the contract bind both the contractor and the Engineer to a short, fixed clock for any concealed condition — prompt notice, parallel procurement of likely materials, and an equally fast Engineer response instructing the Variation and confirming its cost and time consequence — rather than leaving notice at 28 days and the Engineer's response open-ended?

  • Do both the construction contract and the parallel management or franchise agreement bar the brand's technical team from instructing the contractor directly, and require any brand-mandated standard to be routed through the Engineer for pricing before work proceeds?

  • Has the liquidated damages rate been built on a room-revenue calculation retained at signature and, where the project reopens in phases, structured on a sliding scale that reflects the revenue status of each phase, rather than reconstructed after a dispute has started?

  • Have the construction programme and the management agreement's own PIP completion schedule been cross-referenced at drafting stage, so a construction delay and a franchise compliance notice are never a surprise to each other?

  • Is the Taking-Over Certificate trigger fixed in advance to the brand's own technical sign-off, with a joint inspection — Engineer, owner, and brand together — built into the contract as a defined milestone rather than an informal courtesy?

  • Does the payment mechanism require certification and payment of undisputed sums even where a specific line item is contested, rather than allowing an entire application to be withheld?

  • Is an ad hoc DAB mechanism named and resourced at negotiation stage, so a valuation or technical dispute can be resolved in weeks rather than defaulting to arbitration by default?

  • Has each of the clauses above been checked against the specific jurisdiction's civil code and liquidated damages regime, rather than carried over unamended from a template built for a different market or a different project type?


Every item on the checklist above depends on someone inside the owner's organisation actually owning it before the next tender goes out — reading the construction contract and the management agreement together, not in sequence, and being available the moment a brand instruction or a stalled Taking-Over Certificate needs an immediate contractual answer. For a single-asset owner, that case can be made on cost alone. For an owner running several renovations or PIPs across a portfolio, the more valuable case is consistency: instructing different external counsel deal by deal produces different survey clauses, different notice windows, different LD structures, and no institutional memory of which version actually held up when it was tested. A fractional in-house counsel — retained part-time, sitting inside the asset management team rather than outside it — negotiates every renovation and PIP against the same playbook, keeps a live record of which clauses have actually been tested against a contractor or a brand, and is already inside the building when an incident starts rather than being instructed once it has become a dispute.


[1]UAE: Federal Law No. 5 of 1985, Art. 390(2) (old); Federal Decree-Law No. 25 of 2025, Art. 340 (new) — a court or tribunal is empowered, on application, to adjust agreed compensation to the actual loss, and any agreement excluding that power is void. KSA: Civil Transactions Law, Royal Decree No. M/191 of 29 Dhul-Qi'dah 1444H (18 June 2023), Art. 179(2) and (4) — the court may, on the debtor's petition, reduce liquidated damages found to be overestimated or where the underlying obligation was partly performed, and any agreement conflicting with that power is void.

Logo Inverted With Tagline.png
  • LinkedIn

+44 (0)7889 881819

10 North Foreland Road, Broadstairs, CT10 3NN, United Kingdom

© 2026 C&I Dispute Services Ltd - All rights reserved.

C&IDS is a specialist construction lawyer placement provider, not a legal services provider.

bottom of page